Unibera Project Update
  • CALL US : 0120 - 4807800 |Toll Free No. : 1800-120-2006
  • Email ID : info@unibera.com

Your search results

Posted by Admin on December 25, 2013
| News
| 0

Unibera Project Update

You shall glad to know that we have initiated the leveling of land so that the construction could be started properly. There after the system of construction would be followed step by step i.e earmarking of Roads for materials movements, construction equipment movement, after that marking for excavation and extra.

In continuation to it, we are please to update you with the latest developments made so far : –

 

  1. Fire NOC has been received dated-30/10/13 from respected authority Ref no. 254/DD/FS/Meerut-13/1139.
  2. Airport and height NOC has been received dated-13/11/13 from respected authority Ref no. AAI/NOC/2013/489/3184-89.
  3. Environment NOC has been received from the authority Dated-12th Oct/13 Ref no. 1873/parya/SEAC/1727?2013/AD(H) and other important NOC’s has been received from the authority.
  4. Structure vetting from respective authority- done.

Have a look on the latest site pictures in the project photo gallery section. Click here